|
The Niantic River Railroad Bridge Replacement Project
The Niantic River Railroad Bridge replacement project is
moving forward. Amtrak's public statement and it
proposed project description of June 16, 2009, is
presented below. All subsequent documents are linked
from the column on the right of this page.
The State of Connecticut's Notice of Tentative
Determination of September 8, 2009, and comments sent to
the state by the East Lyme Public Trust Foundation
follow the Amtrak project application, which is part of
the state's notice. Following our letter, the Public
Notice by the U.S. Army Corps of Engineers of September
8, 2009 is provided. Our comments on that notice will be
published here as soon as they are submitted to the
Corps.
Amtrak Makes a Public
Commitment of Its Work Program to Replace the Niantic
River Railroad Bridge and to Consequently Re-Install an
Enhanced Niantic Bay Boardwalk
At its first public
Information Meeting concerning the final stage of
Niantic Railroad Bridge replacement, Amtrak
representatives committed to the particulars of its
project at a Camp Rell meeting on June 16, 2009. The
project will have very significant impacts on the
Niantic Bay Boardwalk (a.k.a. Niantic Bay Overlook). In
summary of those Amtrak commitments, and in light of the
required federal and state permit process of which we
are aware, the following major conditions pertain:
1. Amtrak will begin project
construction to complete the replacement of the bridge
and to reinstall the new Goat Path East and the
Boardwalk proper in September of 2009, planning to
conclude that construction within 2 to 4 years, when the
Overlook Park will reopen to public use.
2. During construction, the elevated
portion of the Boardwalk, and the Goat Path East (a
total of about 2,607 feet) will be closed to the
public. The Goat Path West will not be
closed. However, note that the Town of East Lyme
continues its efforts to resolve a mediated
settlement with the designers and constructors of the
Overlook in order for them to correct the faulty design
of that western portion of the Overlook. Their flawed
design of the Goat Path West resulted in storm damage
which continues substantially unabated. The resolution
of that problem has nothing to do with Amtrak nor
with bridge replacement or associated boardwalk and
beach enhancement tasks.
3. Once the Amtrak project is completed,
the main features of its Boardwalk-related aspects will
include:
a) Access to the Boardwalk and its associated sandy
beach by a new passageway under the new bridge that will
be wide enough for emergency vehicles to pass from Cini
Park to the beach and walkway.
b) The existing elevated Boardwalk will be removed and
redesigned/reconstructed as a concrete walkway along the
oceanside railroad elevated embankment. The walkway
will be placed on a step in a new retaining wall that
will protect the walkway from storm damage to a much
greater extent than is presently the case. The walkway
will be the same length and width as is presently the
case. A cross section of this feature appears on Slide
15 of the accompanying Amtrak PowerPoint presentation.
The Foundation will work with the Town, the state and
federal regulatory agencies, and Amtrak to attach to the
surface of the concrete walkway an appropriate
walking/running surface, such as is used on synthetic
track surfaces of athletic fields.
c) Stair and ramp access to the sandy beach will
essentially remain as they are today.
d) A stone groin will be constructed at the eastern end
of the walkway, extending approximately 230 feet long
and 10 feet wide on its top parallel to the river
entrance channel; a structure that will trap sand moving
along the existing beach from west to east and will thus
enlarge and stabilize the beach along the Bar.
e) The 103 memorial benches and the more
than 1,300 memorial plaques will be moved out of harms
way by Amtrak for the duration of construction after
which they will each be returned to there original
position along the Overlook. The location of each
memorial has been documented by the Foundation, which
information will be given to both the Town and Amtrak
during the final project design period.
Should you have any questions or comments, please
contact us: Send
Email l
Top^
|